September 18, 2025
 
Critical Notices
Subject Type Begin Date End Date
The Critical Notices above are active notices posted within the last 14 days. For a complete list of all active critical notices please see Northern's Critical Notices section.
  
 
Pipeline Status Highlights
Market and Field Planned Service Outages — Northern has updated the planned service outages that will affect operating capacity within the months of September 2025 through December 2025 for the Market and Field Areas. Please refer to planned service outage notice #95582 and the Planned Service Outage Summary page for detailed information related to each outage, including the impacted allocation group(s) and/or point(s), direction of flow, normal operating capacity, estimated daily operating capacity during the outage and the anticipated impact to primary firm service. Please continue to review the Planned Service Outage and Planned Service Outage Summary sections on Northern's website for updated information.
  
 
Marketing / Commercial Highlights
No highlights for Thursday, September 18, 2025.
  
 
The Operationally Available Capacity information below includes scheduled quantities and capacities based on the latest cycle processed for the specified gas day. The source data is located on Northern’s Operationally Available Capacity webpage.
ZONE EF
Gas Day Capacity Schd Avail
9/18/202523010477788221522225
9/17/202523010478097351491312
9/16/2025230104710275981273449
GREAT LAKES CARLTON I/C - POI #388
Gas Day Capacity Schd Avail
9/18/202555000030216519784
9/17/202555000060279489721
9/16/202555000082239467761
ZONE D
Gas Day Capacity Schd Avail
9/18/2025644153249209394944
9/17/2025644153228671415482
9/16/2025644153216436427717
FARMINGTON
Gas Day Capacity Schd Avail
9/18/2025989000223131765869
9/17/2025989000239931749069
9/16/2025989000272510716490
ZONE ABC
Gas Day Capacity Schd Avail
9/18/202514230031074121348882
9/17/202514230031140631282372
9/16/202514230031216834206169
VENTURA NORTH
Gas Day Capacity Schd Avail
9/18/202523840005513091832691
9/17/202523840005732201810780
9/16/202523840007877821596218
OGDEN
Gas Day Capacity Schd Avail
9/18/2025100890001008900
9/17/2025100890001008900
9/16/2025100890001008900
OAKLAND
Gas Day Capacity Schd Avail
9/18/202513070002045521102448
9/17/202513070001578851149115
9/16/20251307000332194974806
PALMYRA NORTH
Gas Day Capacity Schd Avail
9/18/2025520100312185207915
9/17/2025520100315515204585
9/16/2025520100289016231084
BEATRICE NORTH
Gas Day Capacity Schd Avail
9/18/20251350000697144652856
9/17/20251350000668780681220
9/16/20251350000920276429724
PALMYRA EAST
Gas Day Capacity Schd Avail
9/18/202514200003587781061222
9/17/202514200003316891088311
9/16/20251420000610503809497
STORAGE (W=Withdrawal,I=Injection)
Gas Day Capacity Schd Avail
9/18/2025I4000006295630
9/17/2025I4000006273620
9/16/2025I40000035116348837

Normal system-weighted temperature: 60
09/17/2025 09/18/2025
69 68
09/19/2025 09/20/2025
65 67
Additional Links
For more detailed information regarding Northern's upcoming planned service outages, capacity constraints or critical notices, please see Northern's Informational Postings.
 
If you have any questions, please contact your customer service or marketing representative. For technical assistance, User ID or password issues please contact Northern's Customer Service: 402-960-7947 or 402-960-7948.
  
 
Accounting / Billing / General Business Highlights
No highlights for Thursday, September 18, 2025.