NNG Logo
Notice Text

Northern has scheduled the service outages that will affect operating capacity within the months of December 2022 through March 2023. Please review the Planned Service Outage Summary for detailed information related to each outage.

 

A brief description of the most recent change(s) to the Planned Service Outage Summary follows.

 

Field Area

Allocation Group(s)/Point(s): Spraberry Station (Group 602)

Location: Spraberry, Texas compressor station

Project Description: Station maintenance

Months: January 2023 through March 2023

Direction of Flow: Receipt

Capacity Impact: Primary firm service will not be impacted.

Revision: Capacity impacts have been added for February 2023 and March 2023.

 

Allocation Group(s)/Point(s): Sunray Low (Group 10) and Sunray High (Group 32)

Location: Sunray, Texas compressor station

Project Description: Station maintenance

Months: February 2023

Direction of Flow: Receipt

Capacity Impact: Primary firm service will not be impacted.

Revision: Capacity impacts have been added for February 2023.

 

Allocation Group(s)/Point(s): Seminole Subsystem (Group 598)

Location: Kermit, Texas compressor station

Project Description: Station maintenance

Months: March 2023

Direction of Flow: Delivery

Capacity Impact: Primary firm service will not be impacted.

 

Please see Operationally Available Capacity on Northern’s website for current flow information and the Field Area Group Allocation Maps and Market Area Group Allocation Maps for a list of impacted points.

 

If you have any questions, contact your customer service or marketing representative.