Northern has scheduled the service outages that will affect operating capacity within the months of December 2022 through January 2023. Please review the Planned Service Outage Summary for detailed information related to each outage.

 

A brief description of the most recent change(s) to the Planned Service Outage Summary follows.

 

Northern received a favorable in-line inspection report related to pipeline maintenance impacting Palmyra North (Group 740). As a result, Northern has updated the Palmyra North (Group 740) operating capacity effective for the Intraday 2 nomination cycle for Gas Day December 20, 2022.

 

Market Area

Allocation Group(s)/Point(s): Palmyra North (Group 740)

Location: Northern’s mainlines between the Palmyra, Nebraska compressor station and the Homer, Nebraska compressor station

Project Description: In-line inspection report

Months: December 2022

Direction of Flow: Delivery

Capacity Impact: Northern does not anticipate primary firm service will be impacted.

Revision: Capacity impacts have been returned to normal for December 2022.

 

Field Area

Allocation Group(s)/Point(s): Spraberry Station (Group 602)

Location: Northern’s Spraberry, Texas compressor station

Project Description: Station maintenance

Months: January 2023

Direction of Flow: Receipt

Capacity Impact: Primary firm service will not be impacted.

 

Please see Operationally Available Capacity on Northern’s website for current flow information and the Field Area Group Allocation Maps and Market Area Group Allocation Maps for a list of impacted points.

 

If you have any questions, contact your customer service or marketing representative.