Northern has scheduled the service outages that will affect operating capacity within the months of November 2020 through January 2021. Please review the Planned Service Outage Summary for detailed information related to each outage.
A brief description of the most recent change(s) to the Planned Service Outage Summary follows.
Northern has completed the maintenance that was impacting Mitchell to Plymouth (Group 760), WTG Sonora Benedum Plants (POI 506) and WTG Shire (POI 79395). As a result, Northern will return the operating capacity levels for the impacted groups to normal operating levels effective for the Intraday 3 cycle for Gas Day November 25, 2020.
Allocation Group(s)/Point(s): Mitchell to Plymouth (Group 760), WTG Sonora Benedum Plants (POI 506) and WTG Shire (POI 79395)
Location: Northern’s mainlines between Reagan County, Texas and the Spraberry, Texas compressor station
Project Description: Pipeline maintenance
Month(s): November 2020
Direction of Flow: Receipt for Mitchell to Plymouth (Group 760) and WTG Sonora Benedum Plants (POI 506), delivery for WTG Shire (POI 79395)
Capacity Impact: Northern anticipates primary firm service will be impacted for Mitchell to Plymouth (Group 760) and WTG Sonora Benedum Plants (POI 506). Primary firm service will not be impacted for WTG Shire (POI 79395).
Revision: Northern has completed the planned maintenance ahead of schedule. Mitchell to Plymouth (Group 760), WTG Sonora Benedum Plants (POI 506) and WTG Shire (POI 79395) will return to normal operating capacity beginning with the Intraday 3 cycle for Gas Day November 25, 2020.
Please see Operationally Available Capacity on Northern’s website for current flow information and the Field Area Group Allocation Maps and Market Area Group Allocation Maps for a list of impacted points.