Northern has scheduled the service outages that will affect operating capacity within the months of November 2020 through January 2021. Please review the Planned Service Outage Summary for detailed information related to each outage.

A brief description of the most recent change(s) to the Planned Service Outage Summary follows.

 

Allocation Group(s)/Point(s): Beaver North (Group 1025) and ANR/NNG Greensburg (POI 179)

Location: Northern’s mainlines between the Beaver, Oklahoma and Mullinville, Kansas compressor stations

Project Description: Pipeline maintenance

Month(s): November 2020

Direction of Flow: Delivery

Capacity Impact: Primary firm service will not be impacted.

Revision: Northern received a favorable in-line inspection report. Beaver North (Group 1025) and ANR/NNG Greensburg (POI 179) will return to normal operating capacity beginning with the Intraday 3 cycle for Gas Day November 17, 2020.

 

Allocation Group(s)/Point(s): Mitchell to Plymouth (Group 760), WTG Sonora Benedum Plants (POI 506) and WTG Shire (POI 79395)

Location: Northern’s mainlines between Reagan County, Texas and the Spraberry, Texas compressor station

Project Description: Pipeline maintenance

Month(s): November 2020

Direction of Flow: Receipt for Mitchell to Plymouth (Group 760) and WTG Sonora Benedum Plants (POI 506), delivery for WTG Shire (POI 79395)

Capacity Impact: Northern anticipates primary firm service will be impacted for Mitchell to Plymouth (Group 760) and WTG Sonora Benedum Plants (POI 506). Primary firm service will not be impacted for WTG Shire (POI 79395).

 

Allocation Group(s)/Point(s): Jal to Gaines (Group 824)

Location: Northern’s mainlines between the Gaines County, Texas and Plains, Texas compressor stations

Project Description: Pipeline maintenance

Months: November through December 2020

Direction of Flow: Receipt

Capacity Impact: Northern does not anticipate primary firm service will be impacted.

Revision: Northern received a favorable in-line inspection report. Jal to Gaines (Group 824)  will return to normal operating capacity beginning with the Intraday 3 cycle for Gas Day November 17, 2020.

 

Allocation Group(s)/Point(s): Sunray Low (Group 10) and Sunray High (Group 32)

Location: Sunray, Texas compressor station

Project Description: Station maintenance at the Sunray, Texas compressor station

Month(s): December 2020 and January 2021

Direction of Flow: Receipt

Capacity Impact: Primary firm service will not be impacted.

Revision: Capacity impacts have been added for January 2021.

 

Allocation Group(s)/Point(s): GSEC Antelope Station Hale Co (POI 79038)

Location: Northern’s pipeline located in Hale County, Texas

Project Description: Pipeline maintenance

Months: December 2020 and January 2021

Direction of Flow: Delivery

Capacity Impact: Northern anticipates primary firm service will be impacted.

Revision: Capacity impacts have been added for January 2021.

 

Please see Operationally Available Capacity on Northern’s website for current flow information and the Field Area Group Allocation Maps and Market Area Group Allocation Maps for a list of impacted points.

If you have any questions, contact your customer service or marketing representative.