Update 2: Northern has identified the issue at the
Claude compressor station and has begun executing a repair plan. Service is
expected to resume early next week. Updates will be provided as the repairs
progress, with the next update coming no later than Friday, May 23, 2025. At
this time, the posted capacity impacts outlined below remain unchanged.
If you have any questions, contact your marketing or
customer service representative.
Update 1: An initial inspection of the Claude
compressor station is ongoing. Northern is currently developing a repair plan,
but does not anticipate the station returning to service prior to next week at
the earliest. Updates will be provided as the repair plan develops, with the
next update coming no later than Monday, May 19, 2025. At this time, the posted
capacity impacts described below remain unchanged.
Original Notice: Northern has experienced a
Force Majeure event at the Claude compressor station located in Claude, Texas,
which requires operating capacities for the Beaver North (Group 1025), Beaver C
and Beaver North (Group 1020), Brownfield North (Group 1022), Pampa North
(Group 1023) and Beaver C System (Group 31) allocation groups to be lowered
effective immediately and until further notice. Incremental nominations for the
allocation groups may not be accepted for the Intraday 3 nomination cycle
for Gas Day Tuesday, May 13, 2025, or the Evening nomination cycle for Gas Day
Wednesday, May 14, 2025. Northern will be required to allocate the groups to
the reduced operating capacities shown below beginning with the Timely
nomination cycle for Gas Day Thursday, May 15, 2025, and continuing until
resolved.
Please continue to monitor Northern's website for updates.
Group Name
|
Group Number
|
Flow Direction
|
Normal Operating Capacity
|
Reduced Operating Capacity
|
Beaver North
|
1025
|
Delivery
|
900,000
|
840,000
|
Beaver C and Beaver North
|
1080
|
Delivery
|
483,000
|
421,000
|
Brownfield North
|
1022
|
Delivery
|
536,000
|
495,000
|
Pampa North
|
1023
|
Delivery
|
483,000
|
421,000
|
Beaver C System
|
31
|
Receipt
|
425,000
|
230,000
|
Please see Operationally
Available Capacity on Northern’s website for
current flow information and the Field Area Group
Allocation Maps for a list of impacted points.