Northern has scheduled the service outages that will affect operating capacity within the months of August 2025 through November 2025. Please review the Planned Service Outage Summary for detailed information related to each outage.
A brief description of the most recent change(s) to the Planned Service Outage Summary follows.
Field Area
Allocation Group(s)/Point(s): Beaver North (Group 1025), Beaver C & Beaver North (Group 1080), Brownfield North (Group 1022), Pampa North (Group 1023), Beaver C System (Group 31) and Mitchell to Gaines (Group 825)
Location: Northern’s compressor stations and mainline between Florey, Texas, and Mullinville, Kansas
Project Description: Station and pipeline maintenance
Month: August 2025 through November 2025
Direction of Flow:
Receipt: Beaver C System (Group 31) and Mitchell to Gaines (Group 825)
Delivery: Beaver North (Group 1025), Beaver C & Beaver North (Group 1080), Brownfield North (Group 1022) and Pampa North (Group 1023)
Capacity Impact: Northern anticipates primary firm service will be impacted for Mitchell to Gaines (Group 825). Northern does not anticipate primary firm service will be impacted for Beaver C & Beaver North (Group 1080), Brownfield North (Group 1022) and Pampa North (Group 1023). Primary firm service will not be impacted for Beaver North (Group 1025) and Beaver C System (Group 31).
Revision: Capacity impacts for Beaver North (Group 1025), Beaver C & Beaver North (Group 1080), Brownfield North (Group 1022), Pampa North (Group 1023) and Beaver C System (Group 31) have been updated for September 2025.
Allocation Group(s)/Point(s): ANR/NNG Greensburg (POI 179) and PEPL/NNG Mullinville (POI 173)
Location: Northern’s mainline and compressor station between Mullinville, Kansas, and Macksville, Kansas
Project Description: Station maintenance
Month: August 2025 through October 2025
Direction of Flow:
Delivery: ANR/NNG Greensburg (POI 179)
Receipt: PEPL/NNG Mullinville (POI 173)
Capacity Impact: Northern anticipates primary firm service will be impacted for ANR/NNG Greensburg (POI 179) . Northern does not anticipate primary firm service will be impacted for PEPL/NNG Mullinville (POI 173).
Revision: Northern anticipates primary firm service will be impacted for ANR/NNG Greensburg (POI 179). Northern does not anticipate primary firm service will be impacted for PEPL/NNG Mullinville (POI 173).
Please see Operationally Available Capacity on Northern’s website for current flow information and the Field Area Group Allocation Maps and Market Area Group Allocation Maps for a list of impacted points.
If you have any questions, contact your customer service or marketing representative.