Northern has scheduled the service outages that will affect operating capacity within the months of July 2025 through November 2025. Please review the Planned Service Outage Summary for detailed information related to each outage.
A brief description of the most recent change(s) to the Planned Service Outage Summary follows.
Market/Field Area Combined
Allocation Group(s)/Point(s): Field to Demarc (Group 831) and Beatrice North (Group 832)
Location: Northern’s mainlines and compressor stations between Mullinville, Kansas, and Ogden, Iowa
Project Description: Pipeline and compressor station maintenance
Month: July 2025 through October 2025
Direction of Flow:
Delivery: Field to Demarc (Group 831) and Beatrice North (Group 832)
Capacity Impact: Northern does not anticipate primary firm service will be impacted for Beatrice North (Group 832) and Field to Demarc (Group 831).
Revision: Capacity impacts for Field to Demarc (Group 831) and Beatrice North (Group 832) have been updated for July 2025.
Field Area
Allocation Group(s)/Point(s): El Paso/NNG Plains 26 DEL (POI 2618) and El Paso/NNG Plains 30” (REC) (POI 57088)
Location: Northern’s meter station in Yoakum County, Texas
Project Description: Station maintenance
Month: July 2025 through August 2025
Direction of Flow:
Delivery: El Paso/NNG Plains 26 DEL (POI 2618)
Receipt: El Paso/NNG Plains 30” (REC) (POI 57088)
Capacity Impact: Northern anticipates primary firm service will be impacted for El Paso/NNG Plains 26 DEL (POI 2618). Northern does not anticipate primary firm service will be impacted for El Paso/NNG Plains 30” (REC) (POI 57088).
Revision: Capacity impacts for El Paso/NNG Plains 30” (REC) (POI 57088) have been updated for July 2025 and August 2025.
Allocation Group(s)/Point(s): Spraberry 12-inch (Group 601), Spraberry 16-inch (Group 1112) and Spraberry Station (Group 602)
Location: Northern’s compressor station in Midland, Texas
Project Description: Station maintenance
Month: July 2025 through September 2025
Direction of Flow:
Delivery: Spraberry 12-inch (Group 601) and Spraberry 16-inch (Group 1112)
Receipt: Spraberry Station (Group 602)
Capacity Impact: Northern anticipates primary firm service will be impacted for Spraberry 12-inch (Group 601), Spraberry 16-inch (Group 1112) and Spraberry Station (Group 602).
Revision: Capacity impacts for Spraberry Station (Group 602) have been updated for July 2025.
Please see Operationally Available Capacity on Northern’s website for current flow information and the Field Area Group Allocation Maps and Market Area Group Allocation Maps for a list of impacted points.
If you have any questions, contact your customer service or marketing representative.