Northern has scheduled the service outages that will affect operating capacity within the months of June 2025 through October 2025. Please review the Planned Service Outage Summary for detailed information related to each outage.
A brief description of the most recent change(s) to the Planned Service Outage Summary follows.
Field Area
Allocation Group(s)/Point(s): Beaver North (Group 1025), Beaver C and Beaver North (Group 1080), Brownfield North (Group 1022), Pampa North (Group 1023), Mitchell to Gaines (Group 825) and Beaver C System (Group 31)
Location: Northern’s compressor stations and mainline between Florey, Texas, and Mullinville, Kansas
Project Description: Station and pipeline maintenance
Month: June 2025 through August 2025
Direction of Flow:
Receipt: Beaver C System (Group 31) and Mitchell to Gaines (Group 825)
Delivery: Beaver North (Group 1025), Beaver C and Beaver North (Group 1080), Brownfield North (Group 1022) and Pampa North (Group 1023)
Capacity Impact: Northern anticipates primary firm service will be impacted for Beaver C and Beaver North (Group 1080), Brownfield North (Group 1022), Pampa North (Group 1023) and Mitchell to Gaines (Group 825). Primary firm service will not be impacted for Beaver North (Group 1025) and Beaver C System (Group 31).
Revision: Capacity impacts for Beaver North (Group 1025), Beaver C and Beaver North (Group 1080), Brownfield North (Group 1022), Pampa North (Group 1023), Mitchell to Gaines (Group 825) and Beaver C System (Group 31) have been updated for June 2025 and July 2025.
Please see Operationally Available Capacity on Northern’s website for current flow information and the Field Area Group Allocation Maps and Market Area Group Allocation Maps for a list of impacted points.
If you have any questions, contact your customer service or marketing representative.