Northern has scheduled the service outages that will affect operating capacity within the months of May 2025 through October 2025. Please review the Planned Service Outage Summary for detailed information related to each outage.

 

A brief description of the most recent change(s) to the Planned Service Outage Summary follows.

Northern has rescheduled compressor station maintenance impacting Viking Chisago/Isanti (POI 196). As a result, capacity impacts for Viking Chisago/Isanti (POI 196) have been updated for June 2025 through August 2025.

 

Market Area

Allocation Group(s)/Point(s): Viking Chisago/Isanti (POI 196)

Location: Northern’s compressor station in North Branch, Minnesota

Project Description: Compressor station maintenance

Month: June 2025 through August 2025

Direction of Flow:

Receipt: Viking Chisago/Isanti (POI 196)

Capacity Impact: Northern anticipates primary firm will be impacted for Viking Chisago/Isanti (POI 196)

Revision: Capacity impacts for Viking Chisago/Isanti (POI 196) have been updated for June 2025 through August 2025.

 

 

Please see Operationally Available Capacity on Northern’s website for current flow information and the Field Area Group Allocation Maps and  Market Area Group Allocation Maps for a list of impacted points.

 

If you have any questions, contact your customer service or marketing representative.