Northern has scheduled the service outages that will affect operating capacity within the month of December 2024 through March 2025. Please review the Planned Service Outage Summary for detailed information related to each outage.
A brief description of the most recent change(s) to the Planned Service Outage Summary follows.
Northern completed compressor station maintenance impacting Beaver North (Group 1025), Beaver C and Beaver North (Group 1080), Brownfield North (Group 1022), Pampa North (Group 1023) and Beaver C System (Group 31) ahead of schedule. As a result, the above mentioned groups will return to normal operating capacities starting with the Intraday 1 nomination cycle for Gas Day Monday, December 23, 2024.
Field Area
Allocation Group(s)/Point(s): Beaver North (Group 1025), Beaver C and Beaver North (Group 1080), Brownfield North (Group 1022), Pampa North (Group 1023) and Beaver C System (Group 31)
Location: Northern’s mainline and compressor station in Claude, Texas
Project Description: Station maintenance
Month: December 2024
Direction of Flow:
Receipt: Beaver C System (Group 31)
Delivery: Beaver North (Group 1025), Beaver C and Beaver North (Group 1080), Brownfield North (Group 1022) and Pampa North (Group 1023)
Capacity Impact: Northern does not anticipate primary firm service will be impacted for Beaver C and Beaver North (Group 1080), Brownfield North (Group 1022) and Pampa North (Group 1032). Primary firm service will not be impacted for Beaver North (Group 1025) and Beaver C System (Group 31).
Revision: Capacity impacts for Beaver North (Group 1025), Beaver C and Beaver North (Group 1080), Brownfield North (Group 1022), Pampa North (Group 1023) and Beaver C System (Group 31) have been updated for December 2024.
Allocation Group(s)/Point(s): Sunray High (Group 32) and Sunray Low (Group 10)
Location: Northern’s Compressor Station in Sunray, Texas
Project Description: Station maintenance
Month: December 2024 and January 2025
Direction of Flow:
Receipt: Sunray High (Group 32) and Sunray Low (Group 10)
Capacity Impact: Primary firm service will not be impacted for Sunray High (Group 32) and Sunray Low (Group 10).
Revision: Capacity impacts for Sunray High (Group 32) and Sunray Low (Group 10) have been updated for January 2025.
Please see Operationally Available Capacity on Northern’s website for current flow information and the Field Area Group Allocation Maps and Market Area Group Allocation Maps for a list of impacted points.
If you have any questions, contact your customer service or marketing representative.