Northern has scheduled the service outages that will affect operating capacity within the months of November 2024 through December 2024. Please review the Planned Service Outage Summary for detailed information related to each outage.

 

A brief description of the most recent change(s) to the Planned Service Outage Summary follows.

Northern completed compressor station maintenance impacting Spraberry 12-inch (Group 601) and Spraberry 16-inch (Group 1112) ahead of schedule. As a result, capacity impacts for the above mentioned groups will return to normal operating capacity beginning with the Intraday 1 nomination cycle for Gas Day Thursday, November 14, 2024.

 

Field Area

Allocation Group(s)/Point(s): Spraberry 12-inch (Group 601) and Spraberry 16-inch (Group 1112)

Location: Northern’s compressor station in Spraberry, Texas

Project Description: Station maintenance

Month: November 2024

Direction of Flow:

Delivery: Spraberry 12-inch (Group 601) and Spraberry 16-inch (Group 1112)

Capacity Impact: Northern does not anticipate primary firm service will be impacted for Spraberry 12-inch (Group 601). Primary firm service will not be impacted for Spraberry 16-inch (Group 1112).

Revision: Capacity impacts for Spraberry 12-inch (Group 601) and Spraberry 16-inch (Group 1112) have been removed from November 2024.

 

 

Please see Operationally Available Capacity on Northern’s website for current flow information and the Field Area Group Allocation Maps and  Market Area Group Allocation Maps for a list of impacted points.

 

If you have any questions, contact your customer service or marketing representative.