Northern has scheduled the service outages that will affect operating capacity within the months of September 2024 through October 2024. Please review the Planned Service Outage Summary for detailed information related to each outage.
A brief description of the most recent change(s) to the Planned Service Outage Summary follows.
Northern completed maintenance impacting Beaver North (Group 1025), Beaver C and Beaver North (Group 1080), Brownfield North (Group 1022), Pampa North (Group 1023) and Beaver C System (Group 31) ahead of schedule. As a result, the above-mentioned groups will return to normal operating capacities for Gas Day September 10, 2024.
Field Area
Allocation Group(s)/Point(s): Beaver North (Group 1025), Beaver C and Beaver North (Group 1080), Brownfield North (Group 1022), Pampa North (Group 1023) and Beaver C System (Group 31)
Location: Northern’s mainline between Claude, Texas and Pampa, Texas
Project Description: Pipeline and station maintenance
Month: September 2024 through October 2024
Direction of Flow:
Receipt: Beaver C System (Group 31)
Delivery: Beaver North (Group 1025), Beaver C and Beaver North (Group 1080), Brownfield North (Group 1022) and Pampa North (Group 1023)
Capacity Impact: Northern anticipates primary firm service will be impacted for Beaver C and Beaver North (Group 1080), Brownfield North (Group 1022), Pampa North (Group 1023). Primary firm service will not be impacted for Beaver North (Group 1025) and Beaver C System (Group 31).
Revision: Capacity impacts for Beaver North (Group 1025), Beaver C and Beaver North (Group 1080), Brownfield North (Group 1022), Pampa North (Group 1023) and Beaver C System (Group 31) have been updated for September 2024.
Please see Operationally Available Capacity on Northern’s website for current flow information and the Field Area Group Allocation Maps and Market Area Group Allocation Maps for a list of impacted points.
If you have any questions, contact your customer service or marketing representative.