Northern has scheduled the service outages that will affect operating capacity within the months of July 2024 through October 2024. Please review the Planned Service Outage Summary for detailed information related to each outage.
A brief description of the most recent change(s) to the Planned Service Outage Summary follows.
Field Area
Allocation Group(s)/Point(s): Mitchell to Gaines (Group 825), Beaver North (Group 1025), Beaver C and Beaver North (Group 1080), Brownfield North (Group 1022), Pampa North (Group 1023), Beaver C System (Group 31), PEPL/NNG Mullinville (POI 173) and ANR/NNG Greensburg (POI 179)
Location: Northern’s mainline and compressor stations between Gaines County, Texas, and Mullinville, Kansas
Project Description: Pipeline and station maintenance
Month: July 2024 through August 2024
Direction of Flow:
Receipt: Mitchell to Gaines (Group 825), Beaver C System (Group 31) and PEPL/NNG Mullinville (POI 173)
Delivery: Beaver North (Group 1025), Beaver C and Beaver North (Group 1080), Brownfield North (Group 1022), Pampa North (Group 1023) and ANR/NNG Greensburg (POI 179)
Capacity Impact: Northern does not anticipate primary firm service will be impacted for Brownfield North (Group 1022), Pampa North (Group 1023), Mitchell to Gaines (Group 825), Beaver C System (Group 31), Beaver C and Beaver North (Group 1080) and PEPL/NNG Mullinville (POI 173). Primary firm service will not be impacted for Beaver North (Group 1025) and ANR/NNG Greensburg (POI 179).
Revision: Capacity impacts for Brownfield North (Group 1022), Pampa North (Group 1023), Beaver North (Group 1025), Beaver C and Beaver North (Group 1080) and Beaver C System (Group 31) have been updated for July 2024.
Allocation Group(s)/Point(s): Sunray High (Group 32), Sunray Low (Group 10) and El Paso/NNG Dumas (POI 186)
Location: Northern’s mainline and compressor stations between Dumas, Texas and Sunray, Texas
Project Description: Pipeline and compressor stations maintenance
Month: July 2024 through October 2024
Direction of Flow:
Receipt: Sunray High (Group 32), Sunray Low (Group 10) and El Paso/NNG Dumas (POI 186)
Capacity Impact: Northern anticipates primary firm service will be impacted for El Paso/NNG Dumas (POI 186). Primary firm service will not be impacted for Sunray High (Group 32) or Sunray Low (Group 10).
Revision: Capacity impacts for El Paso/NNG Dumas (POI 186) have been updated for July 2024.
Allocation Group(s)/Point(s): Spraberry 12-inch (Group 601), Spraberry 16-inch (Group 1112) and Spraberry Station (Group 602)
Location: Compressor station located in Spraberry, Texas as well as pipeline between Plymouth, Texas and Spraberry, Texas
Project Description: Compressor station and pipeline maintenance
Months: July 2024 through September 2024
Direction of Flow:
Delivery: Spraberry 12-inch (Group 601) and Spraberry 16-inch (Group 1112)
Receipt: Spraberry Station (Group 602)
Capacity Impact: Northern does not anticipate that firm service will be impacted for Spraberry 12-inch (Group 601) and Spraberry Station (Group 602). Firm service will not be impacted for Spraberry 16-inch (Group 1112)
Revision: Capacity impacts have been updated for Spraberry Station (Group 602) for July 2024.
Please see Operationally Available Capacity on Northern’s website for current flow information and the Field Area Group Allocation Maps and Market Area Group Allocation Maps for a list of impacted points.
If you have any questions, contact your customer service or marketing representative.