Northern has scheduled the service outages that will affect operating capacity within the months of February 2024 through April 2024. Please review the Planned Service Outage Summary for detailed information related to each outage.

 

A brief description of the most recent change(s) to the Planned Service Outage Summary follows.

 

Market/Field Area Combined

Allocation Group(s)/Point(s): Field to Demarc (Group 831) and Beatrice North (Group 832)

Location: Northern’s mainlines between the Macksville, Kansas, and Bushton, Kansas compressor stations

Project Description: Pipeline maintenance

Month: March 2024 through April 2024

Direction of Flow:

Delivery: Field to Demarc (Group 831) and Beatrice North (Group 832)

Capacity Impact: Northern does not anticipate primary firm service will be impacted for Beatrice North (Group 832). Primary firm service will not be impacted for Field to Demarc (Group 831).

 

Field Area

Allocation Group(s)/Point(s): Beaver North (Group 1025), Beaver C and Beaver North (Group 1080), Brownfield North (Group 1022), Pampa North (Group 1023) and Beaver C System (Group 31)

Location: Northern’s compressor stations located in Plainview, Texas, Claude, Texas, and Pampa, Texas  

Project Description: Station maintenance

Months: February 2024 and April 2024

Direction of Flow:

Delivery: Beaver North (Group 1025), Beaver C and Beaver North (Group 1080), Brownfield North (Group 1022) and Pampa North (Group 1023)

Receipt: Beaver C System (Group 31)

Capacity Impact: Primary firm service will not be impacted for Beaver North (Group 1025) and Beaver C System (Group 31). Northern does not anticipate primary firm service to be impacted for Beaver C and Beaver North (Group 1080), Brownfield North (Group 1022) and Pampa North (Group 1023).

Revision: Capacity impacts for Beaver C and Beaver North (Group 1080), Brownfield North (Group 1022) and Pampa North (Group 1023) have been updated for April 2024.

 

Allocation Group(s)/Point(s): Seminole Subsystem (Group 598), TW/NNG Estes Ward (POI 61334), Oasis/NNG Waha (POI 62148), Agua Blanca Pecos Co (POI 79398), Trans Pecos Hub Pecos Co (POI 79311), ETC Coyanosa (POI 78630), Vaquero Caymus Plant Pecos Co (POI 79303) and ETC Pecos Co (POI 2230)

Location: Northern’s mainline South of the Kermit, Texas compressor station 

Project Description: Pipeline maintenance

Months: March 2024 and April 2024

Direction of Flow:

Delivery: Seminole Subsystem (Group 598)

Receipt: TW/NNG Estes Ward (POI 61334), Oasis/NNG Waha (POI 62148), Agua Blanca Pecos Co (POI 79398), Trans Pecos Hub Pecos Co (POI 79311), ETC Coyanosa (POI 78630), Vaquero Caymus Plant Pecos Co (POI 79303) and ETC Pecos Co (POI 2230)

Capacity Impact: Northern anticipates primary firm service will be impacted for Oasis/NNG Waha (POI 62148), Agua Blanca Pecos Co (POI 79398) and Vaquero Caymus Plant Pecos Co (POI 79303). Northern does not anticipate primary firm service will be impacted for Seminole Subsystem (Group 598). Primary firm service will not be impacted for ETC Coyanosa (POI 78630), TW/NNG Estes Ward (POI 61334), Trans Pecos Hub Pecos Co (POI 79311) and ETC Pecos Co (POI 2230).

Revision: Capacity impacts for Seminole Subsystem (Group 598) have been added in April 2024.

 

Please see Operationally Available Capacity on Northern’s website for current flow information and the Field Area Group Allocation Maps and  Market Area Group Allocation Maps for a list of impacted points.

 

If you have any questions, contact your customer service or marketing representative.