Northern has scheduled the service outages that will affect operating capacity within the months of June 2023 through October 2023. Please review the Planned Service Outage Summary for detailed information related to each outage.

 

A brief description of the most recent change(s) to the Planned Service Outage Summary follows.

 

Market/Field Area Combined

Allocation Group(s)/Point(s): Field to Demarc (Group 831) and Beatrice North (Group 832)

Location: Northern’s mainlines between the Tescott, Kansas and Ogden, Iowa compressor stations

Project Description: Pipeline and station maintenance

Months: June through October 2023

Direction of Flow: Delivery

Capacity Impact: Northern does not anticipate primary firm service will be impacted for Beatrice North (Group 832) and Field to Demarc (Group 831).

Revision: Capacity impacts for Field to Demarc (Group 831) and Beatrice North (Group 832) have been updated for August 2023.

 

Field Area

Allocation Group(s)/Point(s): Sunray High (Group 32) and Sunray Low (Group 10)

Location: Compressor station located in Sunray, Texas

Project Description: Station maintenance

Months: June through August 2023

Direction of Flow:

Receipt: Sunray High (Group 32) and Sunray Low (Group 10)

Capacity Impact: Primary firm service will not be impacted for Sunray High (Group 32) and Sunray Low (Group 10).

 

Allocation Group(s)/Point(s): Beaver North (Group 1025), Beaver C and Beaver North (Group 1080), Brownfield North (Group 1022), and Pampa North (Group 1023)

Location: Pipeline between Gaines County compressor station and Claude compressor stations located in Texas. Compressor station maintenance at the Brownfield compressor station located in Texas.

Project Description: Pipeline and station maintenance

Months: June through August 2023

Direction of Flow:

Delivery: Beaver North (Group 1025), Beaver C and Beaver North (Group 1080), Brownfield North (Group 1022), and Pampa North (Group 1023)

Capacity Impact: Northern does not anticipate primary firm service will be impacted for Beaver C and Beaver North (Group 1080), Brownfield North (Group 1022), and Pampa North (Group 1023). Primary firm service will not be impacted for Beaver North (Group 1025).

 

Allocation Group(s)/Point(s): Enable Redmoon (POI 55168)

Location: Enable Redmoon meter station located in Custer County, Oklahoma

Project Description: Station maintenance

Months: August 2023

Direction of Flow:

Receipts: Enable Redmoon (POI 55168)

Capacity Impact: Northern does not anticipate primary firm service will be impacted for Enable Redmoon (POI 55168).

 

 

Please see Operationally Available Capacity on Northern’s website for current flow information and the Field Area Group Allocation Maps and Market Area Group Allocation Maps  for a list of impacted points.

 

If you have any questions, contact your customer service or marketing representative.