Northern has scheduled the service outages that will affect operating capacity within the months of September 2022 through January 2023. Please review the Planned Service Outage Summary for detailed information related to each outage.
A brief description of the most recent change(s) to the Planned Service Outage Summary follows.
Market Area
Allocation Group(s)/Point(s): Waterloo East (Group 773), Earlville East (Group 487), Galena East (Group 463) and Belleville East (Group 488)
Location: Northern’s mainlines between the Ogden, Iowa compressor station and the Bluff Creek, Wisconsin delivery station
Project Description: Pipeline maintenance and in-line inspection reports
Months: September 2022 through November 2022
Direction of Flow: Delivery
Capacity Impact: Primary firm service will not be impacted.
Revision: Capacity impacts have been updated for October 2022 and added for November 2022.
Allocation Group(s)/Point(s): Palmyra North (Group 740)
Location: Northern’s mainlines between the Palmyra, Nebraska compressor station and the Homer, Nebraska compressor station
Project Description: In-line inspection reports
Months: November 2022 through December 2022
Direction of Flow: Delivery
Capacity Impact: Northern does not anticipate primary firm service will be impacted.
Market/Field Area Combined
Allocation Group(s)/Point(s): Field to Demarc (Group 831) and Beatrice North (Group 832)
Location: Northern’s mainlines between the Tescott, Kansas and Ogden, Iowa compressor stations
Project Description: Pipeline maintenance
Months: September 2022 through January 2023
Direction of Flow: Delivery
Capacity Impact: Primary firm service will not be impacted.
Revision: Capacity impacts have been added for December 2022 through January 2023.
Field Area
Allocation Group(s)/Point(s): Beaver North (Group 1025), Pampa North (Group 1023), Brownfield North (Group 1022), Beaver C System (Group 31), Beaver C and Beaver North (Group 1080), Roger Mills Hemphill System (Group 14) and PEPL/NNG Mullinville (POI 173)
Location: Northern’s mainlines between Clifton, Kansas and Brownfield, Texas, and station maintenance at the Gaines County, Claude, and Pampa compressor stations located in Texas
Project Description: Pipeline and station maintenance
Months: September 2022 through November 2022
Direction of Flow: Delivery for Beaver North (Group 1025), Pampa North (Group 1023), Brownfield North (Group 1022) and Beaver C and Beaver North (Group 1080), and receipt for Beaver C System (Group 31), Roger Mills Hemphill System (Group 14) and PEPL/NNG Mullinville (POI 173)
Capacity Impact: Northern does not anticipate primary firm service will be impacted for Brownfield North (Group 1022), Pampa North (Group 1023), and PEPL/NNG Mullinville (POI 173). Primary firm service will not be impacted for Beaver C and Beaver North (Group 1080), Beaver North (Group 1025), Beaver C System (Group 31), and Roger Mills Hemphill System (Group 14).
Revision: Capacity impacts have been updated for Beaver C System (Group 31) for October 2022 through November 2022.
Allocation Group(s)/Point(s): Sunray Low (Group 10) and Sunray High (Group 32)
Location: Sunray, Texas compressor station
Project Description: Station maintenance
Months: September 2022 through November 2022
Direction of Flow: Receipt
Capacity Impact: Primary firm service will not be impacted.
Revision: Capacity impacts have been updated for October 2022 and November 2022.
Please see Operationally Available Capacity on Northern’s website for current flow information and the Field Area Group Allocation Maps and Market Area Group Allocation Maps for a list of impacted points.
If you have any questions, contact your customer service or marketing representative.