Notice Text
Northern has scheduled the service outages that will affect operating capacity within the months of August 2022 through November 2022. Please review the Planned Service Outage Summary for detailed information related to each outage.

 

A brief description of the most recent change(s) to the Planned Service Outage Summary follows.

 

Northern has completed the station maintenance that was impacting Pampa North (Group 1023) and Brownfield North (Group 1022) ahead of schedule. As a result, Northern will return the operating capacities to normal levels beginning with the Intraday 1 cycle for Gas Day August 25, 2022.

 

Field Area

Allocation Group(s)/Point(s): Beaver North (Group 1025), Pampa North (Group 1023), Brownfield North (Group 1022), Beaver C System (Group 31), Beaver C and Beaver North (Group 1080), Roger Mills Hemphill System (Group 14) and PEPL/NNG Mullinville (POI 173)

Location: Northern’s mainlines between Clifton, Kansas and Brownfield, Texas, and station maintenance at the Gaines County, Claude, and Pampa compressor stations located in Texas

Project Description: Pipeline and station maintenance

Months: August 2022 through November 2022

Direction of Flow: Delivery for Beaver North (Group 1025), Pampa North (Group 1023), Brownfield North (Group 1022) and Beaver C and Beaver North (Group 1080), and receipt for Beaver C System (Group 31), Roger Mills Hemphill System (Group 14) and PEPL/NNG Mullinville (POI 173)

Capacity Impact: Northern anticipates primary firm service will be impacted for Brownfield North (Group 1022) and Pampa North (Group 1023). Northern does not anticipate primary firm service will be impacted for Beaver C and Beaver North (Group 1080) and PEPL/NNG Mullinville (POI 173). Primary firm service will not be impacted for Beaver North (Group 1025), Beaver C System (Group 31), and Roger Mills Hemphill System (Group 14).

Revision: The scheduled maintenance for August 2022 has been completed ahead of schedule. Operating capacities are being returned to normal beginning with the Intraday 1 cycle for Gas Day August 25, 2022.  

Please see Operationally Available Capacity on Northern’s website for current flow information and the Field Area Group Allocation Maps and Market Area Group Allocation Maps for a list of impacted points.

 

If you have any questions, contact your customer service or marketing representative.