Northern has scheduled the service outages that will affect operating capacity within the months of July 2022 through November 2022. Please review the Planned Service Outage Summary for detailed information related to each outage.

A brief description of the most recent change(s) to the Planned Service Outage Summary follows.

 

Northern has completed the pipeline maintenance impacting Brownfield North (Group 1022) and Pampa North (Group 1023) ahead of schedule. As a result, Northern returned the impacted groups to normal operating capacity effective for the Intraday 2 nomination cycle for Gas Day July 22, 2022.

 

Market Area

Allocation Group(s)/Point(s): Waterloo East (Group 773), Earlville East (Group 487), Galena East (Group 463), and Belleville East (Group 488)

Location: Northern’s mainlines between the Ogden, Iowa compressor station and the Bluff Creek, Wisconsin delivery station

Project Description: Pipeline maintenance

Months: July 2022 through October 2022

Direction of Flow: Delivery

Capacity Impact: Primary firm service will not be impacted.

Revision: Capacity impacts have been added for October 2022.

 

Allocation Group(s)/Point(s): REX/NNG Gage County (POI 78929)

Location: Northern’s mainlines between the Clifton, Kansas and the Beatrice, Nebraska compressor stations

Project Description: Pipeline maintenance

Months: August 2022 through September 2022

Direction of Flow: Receipt

Capacity Impact: Primary firm service will not be impacted.

Revision: Capacity impacts have been updated for August 2022 and added for September 2022.

Market/Field Area Combined

Allocation Group(s)/Point(s): Field to Demarc (Group 831) and Beatrice North (Group 832)

Location: Northern’s mainlines between the Tescott, Kansas and Ogden, Iowa compressor stations

Project Description: Pipeline maintenance

Months: July 2022 through November 2022

Direction of Flow: Delivery

Capacity Impact: Primary firm service will not be impacted.

Revision: Capacity impacts have been updated for August 2022.

 

Field Area

Allocation Group(s)/Point(s): Spraberry Station (Group 602), Spraberry 12-inch (Group 601), Spraberry 16-inch (Group 1112), and Mitchell to Plymouth (Group 760)

Location: Spraberry, Texas compressor station

Project Description: Station and pipeline maintenance

Months: July 2022, September 2022, and October 2022

Direction of Flow: Receipt for Spraberry Station (Group 602) and Mitchell to Plymouth (Group 760) and delivery for Spraberry 12-inch (Group 601), Spraberry 16-inch (Group 1112), and Spraberry (Group 600)

Capacity Impact: Northern anticipates primary firm service will be impacted for Spraberry Station (Group 602). Primary firm service will not be impacted for Spraberry 12-inch (Group 601), Spraberry 16-inch (Group 1112), and Mitchell to Plymouth (Group 760).

Revision: Capacity impacts have been removed for August 2022.

 

Allocation Group(s)/Point(s): Beaver North (Group 1025), Pampa North (Group 1023), Brownfield North (Group 1022), Beaver C (Group 31), Beaver C and Beaver North (Group 1080), Roger Mills Hemphill System (Group 14) and PEPL/NNG Mullinville (POI 173)

Location: Northern’s mainlines between Clifton, Kansas and Brownfield, Texas, and station maintenance at the Gaines County, Claude, and Pampa compressor stations located in Texas

Project Description: Pipeline and station maintenance

Months: July 2022 through November 2022

Direction of Flow: Delivery for Beaver North (Group 1025), Pampa North (Group 1023), Brownfield North (Group 1022) and Beaver C and Beaver North (Group 1080), and receipt for Beaver C System (Group 31), Roger Mills Hemphill System (Group 14) and PEPL/NNG Mullinville (POI 173)

Capacity Impact: Northern anticipates primary firm service will be impacted for Brownfield North (Group 1022) and Pampa North (Group 1023). Northern does not anticipate primary firm service will be impacted for Beaver C and Beaver North (Group 1080) and PEPL/NNG Mullinville (POI 173). Primary firm service will not be impacted for Beaver North (Group 1025), Beaver C System (Group 31), and Roger Mills Hemphill System (Group 14).

Revision: Capacity impacts have been updated for July 2022 through November 2022.

 

Allocation Group(s)/Point(s): Mitchell to Gaines (Group 825) and Seminole Subsystem (Group 598)

Location: Northern’s mainline south of Brownfield, Texas and station maintenance at the Gaines County, Texas compressor station

Project Description: Station and pipeline maintenance

Months: September 2022 and November 2022

Direction of Flow: Receipt for Mitchell to Gaines (Group 825) and both receipt and delivery for Seminole Subsystem (Group 598)

Capacity Impact: Northern does not anticipate primary firm service will be impacted for Seminole Subsystem (Group 598). Primary firm service will not be impacted for Mitchell to Gaines (Group 825).

Revision: Capacity impacts have been removed for August 2022.

 

Allocation Group(s)/Point(s): Targa Benedum Plant (POI 183)

Location: Targa Benedum Plant (POI 183)

Project Description: Station maintenance

Months: August 2022

Direction of Flow: Receipt

Capacity Impact: Primary firm service will not be impacted.

Revision: Capacity impacts have been moved from September 2022 to August 2022.

 

Allocation Group(s)/Point(s): Sunray Low (Group 10), Sunray High (Group 32), and ETC Sunray (POI 58676)

Location: Sunray, Texas compressor station

Project Description: Station and pipeline maintenance

Months: July 2022 through November 2022

Direction of Flow: Receipt

Capacity Impact: Primary firm service will be impacted for Sunray Low (Group 10) and ETC Sunray (POI 58676). Primary firm service will not be impacted for Sunray High (Group 32).

Revision: Capacity impacts have been updated for October 2022 and November 2022.

 

Allocation Group(s)/Point(s): Targa Driver Plant (POI 79099)

Location: Targa Driver Plant Interconnect (POI 79099)

Project Description: Station maintenance

Months: August 2022

Direction of Flow: Receipt

Capacity Impact: Primary firm service will not be impacted.

Revision: Capacity impacts have been updated for August 2022.

 

Allocation Group(s)/Point(s): Occidental Permian Hobbs (POI 78415)

Location: Occidental Permian Hobbs (POI 78415)

Project Description: Station maintenance

Months: September 2022

Direction of Flow: Delivery

Capacity Impact: Primary firm service will not be impacted.

Please see Operationally Available Capacity on Northern’s website for current flow information and the Field Area Group Allocation Maps and Market Area Group Allocation Maps  for a list of impacted points.

 

If you have any questions, contact your customer service or marketing representative.