Northern has scheduled the service outages that will affect operating capacity within the months of July 2022 through November 2022. Please review the Planned Service Outage Summary for detailed information related to each outage.
A brief description of the most recent change(s) to the Planned Service Outage Summary follows.
Field Area
Allocation Group(s)/Point(s): ETC Tippett Plant (POI 799)
Location: Northern’s Tippett gathering line
Project Description: Pipeline maintenance
Months: July 2022
Direction of Flow: Receipt
Capacity Impact: Northern anticipates primary firm service will be impacted.
Allocation Group(s)/Point(s): Holcomb Burdette (Group 5) and Sunflower, Kansas No. 1 (POI 50350)
Location: Northern’s mainlines between the Bushton, Kansas compressor station and Garden City, Kansas
Project Description: Pipeline maintenance
Months: August 2022
Direction of Flow: Receipt for Holcomb Burdette (Group 5) and delivery for Sunflower, Kansas No. 1 (POI 50350)
Capacity Impact: Northern does not anticipate primary firm service will be impacted for Holcomb Burdette (Group 5). Primary firm service will not be impacted for Sunflower, Kansas No. 1 (POI 50350).
Revision: Capacity impacts have been updated for August 2022.
Allocation Group(s)/Point(s): CIG/NNG Dumas (POI 360)
Location: Norhtern’s mainlines between Dumas, Texas and the Sunray, Texas compressor station
Project Description: Pipeline maintenance
Months: July 2022
Direction of Flow: Receipt
Capacity Impact: Northern anticipates primary firm service will be impacted.
Please see Operationally Available Capacity on Northern’s website for current flow information and the Field Area Group Allocation Maps and Market Area Group Allocation Maps for a list of impacted points.
If you have any questions, contact your customer service or marketing representative.