NNG Logo
Notice Text

Northern has scheduled the service outages that will affect operating capacity within the months of May 2022 through October 2022. Please review the Planned Service Outage Summary for detailed information related to each outage.

 

A brief description of the most recent change(s) to the Planned Service Outage Summary follows.

 

Field Area

Allocation Group(s)/Point(s): Spraberry Station (Group 602), Spraberry 12-inch (Group 601), and Spraberry 16-inch (Group 1112)

Location: Spraberry, Texas compressor station

Project Description: Station maintenance

Months: May 2022

Direction of Flow: Receipt for Spraberry Station (Group 602) and delivery for Spraberry 12-inch (Group 601) and Spraberry 16-inch (Group 1112)

Capacity Impact: Northern anticipates primary firm service will be impacted.

Revision: Capacity impacts for Spraberry Station (Group 602), Spraberry 12-inch (Group 601), and Spraberry 16-inch (Group 1112) have been updated for May 2022.

 

Allocation Group(s)/Point(s): Sunray Low (Group 10) and Sunray High (Group 32)

Location: Northern’s mainlines between El Paso/NNG Dumas (POI 186) and Northern’s Sunray, Texas compressor station

Project Description: Station and pipeline maintenance

Months: May 2022 through September 2022

Direction of Flow: Receipt

Capacity Impact: Primary firm service will not be impacted.

Revision: Capacity impacts have been updated for May 2022 and June 2022.

 

Please see Operationally Available Capacity on Northern’s website for current flow information and the Field Area Group Allocation Maps and  Market Area Group Allocation Maps   for a list of impacted points.

 

If you have any questions, contact your customer service or marketing representative.