Northern has scheduled the service outages that will affect operating capacity within the months of April 2021 through October 2021. Please review the Planned Service Outage Summary for detailed information related to each outage.

A brief description of the most recent change(s) to the Planned Service Outage Summary follows.

Market Area

Central Mainline

Allocation Group(s)/Point(s): TIGT Milligan (POI 210)

Location: Northern’s Beatrice, Nebraska compressor station

Project Description: Station maintenance

Months: April 2021 through May 2021

Direction of Flow: Receipt and delivery

Capacity Impact: Primary firm service will not be impacted.

Revision: Capacity impacts have been updated for April 2021. 

Field Area

Allocation Group(s)/Point(s): Pampa North (Group 1023), TW/NNG Gray Interconnect (POI 60667), Brownfield North (Group 1022), Mitchell to Gaines (Group 825), Seminole Subsystem (Group 598) and Beaver C and Beaver North (Group 1080)

Location: Northern’s mainlines between the Gaines County, Texas and Beaver, Oklahoma compressor stations, and station maintenance at the Gaines County, Texas compressor station and at TW/NNG Gray Interconnect (POI 60667).

Project Description: Station and pipeline maintenance

Months: April 2021 through June 2021

Direction of Flow: Delivery for Pampa North (Group 1023), Brownfield North (Group 1022), Seminole Subsystem (Group 598) and Beaver C and Beaver North (Group 1080), and receipt for TW/NNG Gray ITE (POI 60667) and Mitchell to Gaines (Group 825)

Capacity Impact: Northern anticipates primary firm service will be impacted for Mitchell to Gaines (Group 825). Northern does not anticipate primary firm service will be impacted for Pampa North (Group 1023), Brownfield North (Group 1022) and Seminole Subsystem (Group 598). Primary firm service will not be impacted for TW/NNG Gray ITE (POI 60667) and Beaver C and Beaver North (Group 1080).

Revision: Capacity impacts have been added for Beaver C and Beaver North (Group 1080) for April 2021.

Please see Operationally Available Capacity on Northern’s website for current flow information and the Field Area Group Allocation Maps and Market Area Group Allocation Maps for a list of impacted points. 

If you have any questions, contact your customer service or marketing representative.