NNG Logo
Notice Text

Northern has scheduled the service outages that will affect operating capacity within the months of September 2020 through December 2020. Please review the Planned Service Outage Summary for detailed information related to each outage. 

A brief description of the most recent change(s) to the Planned Service Outage Summary follows. 

Market Area

Ogden North

Allocation Group(s)/Point(s): Carlton South (Group 811)

Location: Northern’s mainlines between the North Branch, Minnesota and Carlton, Minnesota compressor stations.

Project Description: Pipeline maintenance

Month(s): September 2020 and October 2020

Direction of Flow: Receipt

Capacity Impact: Primary firm service will not be impacted.

Revision: Capacity impacts have been added for October 2020. 

East Leg

Allocation Group(s)/Point(s): Earlville East (Group 487) and Belleville East (Group 488)

Location: Earlville, Iowa compressor station

Project Description: Station maintenance

Month(s): November 2020

Direction of Flow: Delivery

Capacity Impact: Northern does not anticipate primary firm service will be impacted for Earlville East (Group 487). Primary firm service will not be impacted for Belleville East (Group 488). 

Market/Field Area Combined

Allocation Group(s)/Point(s): Field to Demarc (Group 831) and Beatrice North (Group 832)

Location: Northern’s mainlines between the Clifton, Kansas and Ogden, Iowa compressor stations. In addition, the Palmyra, Nebraska compressor station will undergo maintenance.

Project Description: Station maintenance at the Palmyra, Nebraska compressor station and pipeline maintenance

Month(s): September 2020 through November 2020

Direction of Flow: Delivery

Capacity Impact: Primary firm service will not be impacted.

Revision: Capacity impacts have been updated for October 2020 and November 2020.

 

Field Area

Allocation Group(s)/Point(s): Beaver North (Group 1025), Beaver C System (Group 31), Beaver System South (Group 13), Brownfield North (Group 1022), Pampa North (Group 1023), PEPL/NNG Mullinville (POI 173), ANR/NNG Greensburg (POI 179) and Mitchell to Gaines (Group 825)

Location: Beaver, Oklahoma and Mullinville, Kansas compressor stations

Project Description: Station modifications and in-line inspection modifications between the Beaver, Oklahoma and Mullinville, Kansas compressor stations

Month(s): September 2020 through November 2020

Direction of Flow: Delivery for Beaver North (Group 1025), Brownfield North (Group 1022),  Pampa North (Group 1023), and ANR/NNG Greensburg (POI 179) and receipt for Beaver C System (Group 31), Beaver System South (Group 13), PEPL/NNG Mullinville (POI 173) and Mitchell to Gaines (Group 825).

Capacity Impact: Northern anticipates primary firm service will be impacted for Mitchell to Gaines (Group 825), Brownfield North (Group 1022) and Pampa North (Group 1023). Northern does not anticipate primary firm service will be impacted for Beaver System South (Group 13) and PEPL/NNG Mullinville (POI 173). Primary firm service will not be impacted for Beaver C System (Group 31), Beaver North (Group 1025) and ANR/NNG Greensburg (POI 179).

Revision: Capacity impacts have been updated for October 2020 and November 2020. 

Allocation Group(s)/Point(s): Sunray Low (Group 10) and Sunray High (Group 32)

Location: Sunray, Texas compressor station

Project Description: Station maintenance at the Sunray, Texas compressor station

Month(s): September 2020 through December 2020

Direction of Flow: Receipt

Capacity Impact: Primary firm service will not be impacted.

Revision: Capacity impacts have been added for December 2020. 

Allocation Group(s)/Point(s): El Paso Waha, Texas (POI 57100)

Location: Station maintenance at the El Paso Waha (POI 57100)

Project Description: Station maintenance

Month(s): October 2020

Direction of Flow: Delivery

Capacity Impact: Northern anticipates primary firm service will be impacted.

 

Please see Operationally Available Capacity on Northern’s website for current flow information and the Field Area Group Allocation Maps and Market Area Group Allocation Maps for a list of impacted points. 

If you have any questions, contact your customer service or marketing representative.