Northern has scheduled the service outages that will affect operating capacity within the months of August 2020 through November 2020. Please review the Planned Service Outage Summary for detailed information related to each outage.

A brief description of the most recent change(s) to the Planned Service Outage Summary follows.

 

Northern has received a favorable in-line inspection report that was impacting Mankato Energy Center (POI 78553). As a result, Northern will return the operating capacity level for the impacted point to normal operating levels effective for the Intraday 2 cycle for Gas Day August 7, 2020.

 

Market Area

Ogden North

Allocation Group(s)/Point(s): Mankato Energy Center (POI 78553)

Location: Northern’s mainline between Welcome and Minneapolis, Minnesota

Project Description: Pipeline maintenance

Month(s): August 2020

Direction of Flow: Delivery

Capacity Impact: Northern anticipates primary firm service will be impacted.

Revision: Capacity impacts for Mankato Energy Center have been removed.

 

Please see Operationally Available Capacity on Northern’s website for current flow information and the Field Area Group Allocation Maps and Market Area Group Allocation Maps for a list of impacted points.

If you have any questions, contact your customer service or marketing representative.