Northern has scheduled the service outages that will affect operating capacity within the months of July 2020 through November 2020. Please review the Planned Service Outage Summary for detailed information related to each outage.

 

A brief description of the most recent change(s) to the Planned Service Outage Summary follows.

 

Market Area

Ogden North

Allocation Group(s)/Point(s): Mankato Energy Center (POI 78553)

Location: Northern’s mainline between Welcome and Minneapolis, Minnesota

Project Description: Pipeline maintenance

Month(s): June 2020 and July 2020

Direction of Flow: Delivery

Capacity Impact: Northern anticipates primary firm service will be impacted.

Revision: Capacity impacts have been removed for July 2020 and added for August 2020.

 

Central Mainline

Allocation Group(s)/Point(s): TIGT Milligan (POI 210)

Location: Palmyra, Nebraska

Project Description: Station maintenance at the Palmyra, Nebraska compressor station and pipeline maintenance

Month(s): July 2020 through August 2020

Direction of Flow: Receipt

Capacity Impact: Primary firm service will not be impacted.

Revision: The capacity impacts for July 2020 and August 2020 have been removed.

 

Field Area

Allocation Group(s)/Point(s): Sunray Low (Group 10) and Sunray High (Group 32)

Location: Spraberry, Texas compressor station

Project Description: Station maintenance at the Spraberry, Texas compressor station

Month(s): May 2020 through August 2020

Direction of Flow: Receipt

Capacity Impact: Primary firm service will not be impacted.

Revision: Capacity impacts have been added for August 2020.

 

Please see Operationally Available Capacity on Northern’s website for current flow information and the Field Area Group Allocation Maps and Market Area Group Allocation Maps for a list of impacted points. 

If you have any questions, contact your customer service or marketing representative.