Northern has scheduled the service outages that will affect operating capacity within the months of June 2020 through November 2020. Please review the Planned Service Outage Summary for detailed information related to each outage.

A brief description of the most recent change(s) to the Planned Service Outage Summary follows.

 

Field Area

   Allocation Group(s)/Point(s): GCX Waha (POI 79415)

   Location: Pecos County, Texas

   Project Description: Pipeline maintenance near GCX Waha

   Month(s): June 2020 and July 2020

   Direction of Flow: Delivery

   Capacity Impact: Primary firm service will not be impacted.

   Revision: Capacity impact has been added for July 2, 2020.

 

Please see Operationally Available Capacity on Northern’s website for current flow information and the Field Area Group Allocation Maps and Market Area Group Allocation Maps for a list of impacted points. 

 