Northern has scheduled the service outages that will affect operating capacity within the months of March 2020 through October 2020. Please review the Planned Service Outage Summary for detailed information related to each outage.
A brief description of the most recent change(s) to the Planned Service
Outage Summary follows.
Allocation
Group(s)/Point(s): TIGT Milligan
(POI 210)
Location: Palmyra, Nebraska
Project Description: Station maintenance at the Palmyra, Nebraska compressor station and
pipeline maintenance
Month(s): June 2020
Direction of Flow: Receipt
Capacity
Impact: Primary firm service will not be
impacted.
Market/Field Area Combined
Allocation
Group(s)/Point(s): Field to Demarc
(Group 831) and Beatrice North (Group 832)
Location: Northern’s mainlines between the
Clifton, Kansas and Ogden, Iowa compressor stations. In addition, the Palmyra, Nebraska compressor station will
undergo maintenance.
Project Description: Station maintenance at the Palmyra, Nebraska compressor station and
pipeline maintenance
Month(s): March 2020 through October 2020
Direction of Flow: Delivery
Capacity
Impact: Primary firm service will not be
impacted.
Revision: Capacity impacts for Field to Demarc
(Group 831) have been updated for April 2020 and May 2020. Capacity impacts for
Beatrice North (Group 832) have been updated for April 2020 and June 2020.
Field Area
Allocation
Group(s)/Point(s): Spraberry
12-inch (Group 601) and Spraberry Station (Group 602)
Location: Spraberry, Texas compressor
station
Project
Description: Station
maintenance at the Spraberry, Texas compressor station
Month(s): April 2020 through June 2020
Direction
of Flow: Delivery for Spraberry 12-inch (Group 601)
and receipt for Spraberry Station (Group 602)
Capacity
Impact: Northern anticipates primary firm service capacity
will be impacted.
Revision: Capacity impacts for Spraberry Station
(Group 602) have been removed from April 2020 to June 2020. Capacity impacts
for Spraberry 12-inch (Group 601) have been added for June 2020.
Allocation
Group(s)/Point(s): Sunray Low
(Group 10), Sunray High (Group 32) and Beaver C System (Group 31)
Location: Sunray, Texas compressor station
Project
Description: Station
maintenance at the Sunray, Texas compressor station
Month(s): April 2020 through June 2020
Direction
of Flow: Receipt
Capacity Impact:
Northern anticipates primary firm service will be impacted for Sunray Low
(Group 10). Northern does not anticipate primary firm service will be
impacted for Sunray High (Group 32) and Beaver C System (Group 31).
Revision: Capacity impacts for Sunray Low (Group
10) and Sunray High (Group 32) have been added for June 2020.
The operating
capacities include the total of both transportation and operational storage
capacity. Any unused operational storage capacity can be used for
transportation volumes on a daily basis. Should conditions require Northern to
use more of the operational storage capacity than anticipated, the operating
capacities available for transportation will be reduced.
Please see Operationally Available Capacity on Northern’s website for current flow information and the
Field Area Group Allocation Maps and Market Area Group Allocation Maps
for a list of impacted points.
If
you have any questions, contact your customer service or marketing
representative.