Northern has scheduled the planned service outages that will
affect operating capacity within the months of December 2019 through February
2020. Please review the Planned
Service Outage Summary for detailed information related to each outage.
A brief description of the most recent change(s) to the Planned
Service Outage Summary follows.
Northern
has completed the maintenance that was impacting the Sunray Low (Group 10) and
Sunray High (Group 32) allocation groups. As a result, Northern will return the
groups’ operating capacities to normal levels beginning with Gas Day December 5, 2019 for the
Intraday 1 cycle.
Field Area Allocation Group(s)/Point(s): Sunray Low (Group 10) and Sunray High (Group 32) Location: Sunray, Texas compressor station Project Description: Station maintenance at the Sunray, Texas compressor station Month(s): December 2019 Direction of Flow: Receipt Capacity Impact: Northern anticipates primary firm service will be impacted. Note: Northern will not have operational flexibility to
increase receipts in Sunray Low (Group 10). Revision: The scheduled maintenance impacting the Sunray Low (Group 10) and Sunray High (Group 32) allocation groups has
been completed ahead of schedule.
Please see Operationally Available Capacity on Northern’s website for current flow information and the
Field Area Group Allocation Maps and Market Area Group Allocation Maps for a list of impacted points.
If
you have any questions, contact your customer service or marketing
representative.