Notice Text:
Northern has scheduled the
following service outages that will affect operating capacity within the months
of October 2025 through December 2025. Please review the
Planned Service Outage Summary for detailed information related to each
outage.
A brief description of the
most recent change(s) to the Planned Service Outage Summary follows.
Field Area
Allocation Group(s)/Point(s):
Sunray Low (Group 10), Sunray High (Group 32) and ETC
Sunray Plant (POI 58676)
Location:
Northern’s compressor station in Sunray, Texas
Project Description:
Station maintenance
Month:
October 2025
Direction of Flow:
Receipt: Sunray Low (Group 10),
Sunray High (Group 32) and ETC Sunray Plant (POI 58676)
Capacity Impact: Northern anticipates
primary firm service will be impacted for Sunray Low (Group 10) and ETC Sunray
Plant (POI 58676).
Northern does not anticipate primary
firm service will be impacted for Sunray High (Group 32).
Revision:
Capacity impacts for Sunray Low (Group 10) and Sunray
High (Group 32) have been updated for October 2025. Capacity impacts for ETC
Sunray Plant (POI 58676) have been included for October 2025.
Please see
Operationally
Available Capacity on Northern’s website for current flow information and the
Field
Area Group Allocation Maps and
Market
Area Group Allocation Maps for a list of impacted points.
If you have any questions, contact your customer service or
marketing representative.
|