TSP Name:   Northern Natural Gas Company
TSP:   784158214
Notice ID:   094940
Notice Type:   Planned Service Outage
Subject:   PLANNED SERVICE OUTAGES – SEPTEMBER 2025 THROUGH NOVEMBER 2025
Critical:   N
Location:   MARKET AND FIELD AREA
Post Date/Time:   09/04/2025 10:00 AM
Notice Effective Date/Time:   09/04/2025 10:00 AM
Notice End Date/Time:   09/08/2025 01:35 PM
For Gas Day(s):   09/04/2025 - 09/08/2025
Notice Status:   Terminate
Prior Notice:   094657
Required Response Indicator Description:   5-No response required
Notice Text:

Northern has scheduled the service outages that will affect operating capacity within the months of September 2025 through November 2025. Please review the Planned Service Outage Summary for detailed information related to each outage.

 

A brief description of the most recent change(s) to the Planned Service Outage Summary follows.

Northern postponed the outage at Pampa, Texas, compressor station impacting Beaver North (Group 1025), Beaver C & Beaver North (Group 1080), Brownfield North (Group 1022), Pampa North (Group 1023) and Beaver C System (Group 31). As a result, capacity impacts for the above-mentioned groups have been removed for Gas Day September 5, 2025.

 

Field Area

Allocation Group(s)/Point(s): Beaver North (Group 1025), Beaver C & Beaver North (Group 1080), Brownfield North (Group 1022), Pampa North (Group 1023) and Beaver C System (Group 31)

Location: Northern’s compressor stations and mainline between Florey, Texas, and Mullinville, Kansas

Project Description: Station and pipeline maintenance

Month: September 2025 through November 2025

Direction of Flow:

       Receipt: Beaver C System (Group 31)

Delivery: Beaver North (Group 1025), Beaver C & Beaver North (Group 1080), Brownfield North (Group 1022) and Pampa North (Group 1023)

Capacity Impact: Northern does not anticipate primary firm service will be impacted for Beaver C & Beaver North (Group 1080), Brownfield North (Group 1022) and Pampa North (Group 1023). Primary firm service will not be impacted for Beaver North (Group 1025) and Beaver C System (Group 31).

Revision: Capacity impacts for Beaver North (Group 1025), Beaver C & Beaver North (Group 1080), Brownfield North (Group 1022), Pampa North (Group 1023) and Beaver C System (Group 31) have been updated for September 2025.

 

Please see Operationally Available Capacity on Northern’s website for current flow information and the Field Area Group Allocation Maps and  Market Area Group Allocation Maps for a list of impacted points.

 

If you have any questions, contact your customer service or marketing representative.