Northern has scheduled the
service outages that will affect operating capacity within the months of July 2025
through November 2025. Please review the
Planned Service Outage Summary for detailed information related to each
outage.
A brief description of the
most recent change(s) to the Planned Service Outage Summary follows.
Market Area
Allocation Group(s)/Point(s):
Ventura South (Group 735)
Location:
Northern’s pipelines and compressor stations between
Ogden, Iowa, and Farmington, Minnesota
Project Description:
Pipeline and compressor station maintenance
Month:
July 2025 through October 2025
Direction of Flow:
Delivery:
Ventura South (Group 735)
Capacity Impact:
Northern does not anticipate primary firm service will be impacted
for Ventura South (Group 735)
Revision: Capacity impacts for
Ventura South (Group 735) have been updated for September 2025.
Field Area
Allocation Group(s)/Point(s):
Beaver North (Group 1025), Beaver C & Beaver North
(Group 1080), Brownfield North (Group 1022), Pampa North (Group 1023), Beaver C
System (Group 31) and Mitchell to Gaines (Group 825)
Location:
Northern’s compressor stations and mainline between
Florey, Texas, and Mullinville, Kansas
Project Description:
Station and pipeline maintenance
Month:
July 2025 through November 2025
Direction of Flow:
Receipt: Beaver C System (Group 31) and Mitchell to Gaines (Group 825)
Delivery: Beaver North (Group 1025),
Beaver C & Beaver North (Group 1080), Brownfield North (Group 1022) and
Pampa North (Group 1023)
Capacity Impact: Northern anticipates
primary firm service will be impacted for Mitchell to Gaines (Group 825).
Northern does not anticipate primary firm service will be
impacted for Beaver C & Beaver North (Group 1080), Brownfield North (Group
1022) and Pampa North (Group 1023). Primary firm service will not be
impacted for Beaver North (Group 1025) and Beaver C System (Group 31).
Revision:
Capacity impacts for Beaver North (Group 1025), Beaver
C & Beaver North (Group 1080), Brownfield North (Group 1022), Pampa North
(Group 1023) and Beaver C System (Group 31) have been updated for August 2025.
Capacity impacts for Mitchell to Gaines (Group 825) have been included for
August 2025.
Allocation Group(s)/Point(s):
Sunray High (Group 32) and Sunray Low (Group 10)
Location:
Northern’s compressor station in Sunray, Texas
Project Description:
Pipeline and compressor station maintenance
Months:
August 2025 and September 2025
Direction of Flow:
Receipt: Sunray High (Group 32) and
Sunray Low (Group 10)
Capacity Impact:
Primary firm service will not be impacted for Sunray High
(Group 32) and Sunray Low (Group 10).
Revision:
Capacity impacts for Sunray High (Group 32) and Sunray
Low (Group 10) have been removed for August 2025 and updated for September
2025.
Please see
Operationally Available Capacity on
Northern’s website for current flow information and the
Field Area Group Allocation Maps and
Market Area Group Allocation Maps for a list of impacted points.
If you have any questions, contact your customer service or
marketing representative.