Northern has scheduled the
service outages that will affect operating capacity within the months of April
2026 through October 2026. Please review the
Planned Service Outage Summary for detailed information related to each
outage.
A brief description of the
most recent change(s) to the Planned Service Outage Summary follows.
Market/Field Area Combined
Allocation Group(s)/Point(s):
Field to Demarc (Group 831) and Beatrice North (Group 832)
Location:
Northern’s pipelines and compressor stations located
between the Mullinville, Kansas, and Ogden, Iowa, compressor stations
Project Description:
Compressor station and pipeline maintenance
Month:
April 2026 through October 2026
Direction of Flow:
Delivery: Field to Demarc (Group 831)
and Beatrice North (Group 832)
Capacity Impact:
Northern does not anticipate primary firm service will be
impacted for Beatrice North (Group 832) and Field to Demarc (Group 831).
Revision: Capacity impacts for Field
to Demarc (Group 831) and Beatrice North (Group 832) have been updated for August
2026.
Field Area
Allocation Group(s)/Point(s):
Beaver North (Group 1025), Beaver C and Beaver System
North (Group 1080), Brownfield North (Group 1022), Pampa North (Group 1023) and
Beaver C System (Group 31)
Location:
Northern’s compressor stations and pipeline between
Florey, Texas, and Beaver, Oklahoma
Project Description:
Compressor station maintenance
Month:
April 2026 through June 2026
Direction of Flow:
Delivery: Beaver North (Group 1025),
Beaver C and Beaver System North (Group 1080), Brownfield North (Group 1022)
and Pampa North (Group 1023)
Receipt: Beaver C System (Group 31)
Capacity Impact: Primary service will
be impacted for Brownfield North (Group 1022) and Pampa North (1023).
Northern does not anticipate primary firm service will be
impacted for Beaver C and Beaver System North (Group 1080). Primary firm
service will not be impacted for Beaver North (Group 1025) and Beaver C System
(Group 31).
Revision: Capacity impacts for Beaver
North (Group 1025) have been updated for April 2026.
Allocation Group(s)/Point(s):
PEPL/NNG Mullinville (POI 173) and ANR/NNG Greensburg (POI
179)
Location:
Northern’s compressor station located in Mullinville,
Kansas
Project Description:
Compressor station maintenance
Month:
April 2026 through June 2026
Direction of Flow:
Delivery:
ANR/NNG Greensburg (POI 179)
Receipt:
PEPL/NNG Mullinville (POI 173)
Capacity Impact:
Northern does not anticipate primary firm service will be
impacted for PEPL/NNG Mullinville (POI 173). Primary firm service will not be
impacted for ANR/NNG Greensburg (POI 179).
Revision: Capacity impacts for PEPL/NNG
Mullinville (POI 173) and ANR/NNG Greensburg (POI 179) have been updated for
April 2026.
Please see
Operationally Available Capacity on
Northern’s website for current flow information and the
Field Area Group Allocation Maps and
Market Area Group Allocation Maps for a list of impacted points.
If you have any
questions, contact your customer service or marketing representative.