Northern has scheduled the
service outages that will affect operating capacity within the months of March
2026 through October 2026. Please review the
Planned Service Outage Summary for detailed information related to each
outage.
A brief description of the
most recent change(s) to the Planned Service Outage Summary follows.
Market/Field Area Combined
Allocation Group(s)/Point(s):
Field to Demarc (Group 831) and Beatrice North (Group 832)
Location:
Northern’s pipelines and compressor stations located
between the Mullinville, Kansas, and Ogden, Iowa, compressor stations
Project Description:
Compressor station and pipeline maintenance
Month:
April 2026 through October 2026
Direction of Flow:
Delivery: Field to Demarc (Group 831)
and Beatrice North (Group 832)
Capacity Impact:
Northern does not anticipate primary firm service will be
impacted for Beatrice North (Group 832) and Field to Demarc (Group 831).
Revision: Capacity impacts for Field
to Demarc (Group 831) and Beatrice North (Group 832) have been updated for
April 2026.
Field Area
Allocation Group(s)/Point(s):
Beaver North (Group 1025)
Location:
Northern’s compressor station located in Beaver, Kansas
Project Description:
Compressor station maintenance
Month:
April 2026 through June 2026
Direction of Flow:
Delivery: Beaver North (Group 1025)
Capacity Impact:
Primary firm service will not be impacted for Beaver North
(Group 1025).
Revision: Capacity impacts for Beaver
North (Group 1025) have been included for April 2026.
Allocation Group(s)/Point(s):
PEPL/NNG Mullinville (POI 173) and ANR/NNG Greensburg (POI
179)
Location:
Northern’s compressor station located in Mullinville,
Kansas
Project Description:
Compressor station maintenance
Month:
April 2026 through June 2026
Direction of Flow:
Delivery:
ANR/NNG Greensburg (POI 179)
Receipt:
PEPL/NNG Mullinville (POI 173)
Capacity Impact:
Northern does not anticipate primary firm service will be
impacted for PEPL/NNG Mullinville (POI 173). Primary firm service will not be
impacted for ANR/NNG Greensburg (POI 179).
Revision: Capacity impacts for PEPL/NNG
Mullinville (POI 173) and ANR/NNG Greensburg (POI 179) have been included for
April 2026.
Please see
Operationally
Available Capacity on Northern’s website for current flow information and the
Field
Area Group Allocation Maps and
Market
Area Group Allocation Maps for a list of impacted points.
If you have any questions, contact your customer service or
marketing representative.