Northern has scheduled the
service outages that will affect operating capacity within the months of March
2026 through October 2026. Please review the
Planned Service Outage Summary
for detailed information related to each
outage.
A brief description of the
most recent change(s) to the Planned Service Outage Summary follows.
Market/Field Area Combined
Allocation Group(s)/Point(s):
Field to Demarc (Group 831) and Beatrice North (Group 832)
Location:
Northern’s pipelines and compressor stations located
between the Mullinville, Kansas, and Ogden, Iowa, compressor stations
Project Description:
Compressor station and pipeline maintenance
Month:
April 2026 through October 2026
Direction of Flow:
Delivery: Field to Demarc (Group 831)
and Beatrice North (Group 832)
Capacity Impact:
Northern does not anticipate primary firm service will be
impacted for Beatrice North (Group 832) and Field to Demarc (Group 831).
Revision: Capacity impacts for Field
to Demarc (Group 831) and Beatrice North (Group 832) have been updated for May
2026 and June 2026.
Market Area
Allocation Group(s)/Point(s):
Ventura South (Group 735)
Location:
Northern’s pipelines and compressor stations between
Ventura, Iowa, and Ogden, Iowa
Project Description:
Pipeline maintenance
Month:
April 2026 through June 2026
Direction of Flow:
Delivery:
Ventura South (Group 811)
Capacity
Impact:
Northern does not anticipate primary
firm service will be impacted for Ventura South (Group 735).
Revision: Capacity impacts for
Ventura South (Group 735) have been updated for May 2026 and June 2026.
Allocation Group(s)/Point(s):
Waterloo East (Group 773), Earlville East (Group 487),
Galena East (Group 463) and Belleville East (Group 488)
Location:
Northern’s pipelines and compressor stations between
Waterloo, Iowa, and Belleville, Iowa
Project Description:
Compressor station and pipeline maintenance
Month:
April 2026 through October 2026
Direction of Flow:
Delivery: Waterloo East (Group 773),
Earlville East (Group 487), Galena East (Group 463) and Belleville East (Group
488)
Capacity Impact:
Northern does not anticipate primary firm service will be
impacted for Waterloo East (Group 773), Earlville East (Group 487), Galena East
(Group 463) and Belleville East (Group 488).
Revision: Capacity impacts for Waterloo
East (Group 773), Earlville East (Group 487), Galena East (Group 463) and
Belleville East (Group 488) have been updated for May 2026 and June 2026.
Capacity impacts for Waterloo East (Group 773), Earlville East (Group 487),
Galena East (Group 463) and Belleville East (Group 488) have been included for
July 2026 through October 2026.
Field Area
Allocation Group(s)/Point(s):
Beaver North (Group 1025), Beaver C & Beaver North
(Group 1080), Brownfield North (Group 1022), Pampa North (Group 1023), Beaver C
System (Group 31) and Mitchell to Gaines (Group 825)
Location:
Northern’s compressor stations and pipeline between
Florey, Texas, and Mullinville, Kansas
Project Description:
Compressor station and pipeline maintenance
Month:
May 2026 and June 2026
Direction of Flow:
Delivery: Beaver North (Group 1025),
Beaver C & Beaver North (Group 1080), Brownfield North (Group 1022) and
Pampa North (Group 1023)
Receipt:
Beaver C System (Group 31) and Mitchell to Gaines (Group 825)
Capacity Impact: Primary firm service
will be impacted for Brownfield North (Group 1022) and Pampa North (Group 1023).
Primary firm service will not be
impacted for Beaver North (Group 1025) and Beaver C System (Group 31). Northern
does not anticipate primary firm service will be impacted for Beaver C and
Beaver System North (Group 1080).
Revision: Capacity impacts for Beaver
North (Group 1025), Beaver C & Beaver North (Group 1080), Brownfield North
(Group 1022), Pampa North (Group 1023), Beaver C System (Group 31) and Mitchell
to Gaines (Group 825) have been updated for May 2026 and included for June
2026.
Allocation Group(s)/Point(s):
ANR/NNG Greensburg (POI 179)
Location:
Northern’s compressor station located in Mullinville,
Kansas
Project Description:
Compressor station maintenance
Month:
May 2026 through June 2026
Direction of Flow:
Delivery:
ANR/NNG Greensburg (POI 179)
Capacity Impact:
Primary firm service will not be impacted for ANR/NNG
Greensburg (POI 179).
Revision: Capacity impacts for ANR/NNG
Greensburg (POI 179) have been updated for May 2026 and included for June 2026.
Allocation Group(s)/Point(s):
Sunray Low (Group 10) and Sunray High (Group 32)
Location:
Northern’s compressor station located in Sunray, Texas
Project Description:
Compressor station and pipeline maintenance
Month:
April 2026 through June 2026
Direction of Flow:
Receipt:
Sunray Low (Group 10) and Sunray High (Group 32)
Capacity Impact: Primary firm service
will be impacted for Sunray Low (Group 10).
Primary
firm service will not be impacted for Sunray High (Group 32).
Revision: Capacity impacts for Sunray
Low (Group 10) and Sunray High (Group 32) have been included for June 2026.
Allocation Group(s)/Point(s):
Spraberry 12-inch (Group 601), Spraberry 16-inch (Group
1112) and Spraberry Station (Group 602)
Location:
Northern’s compressor station located in Spraberry, Texas
Project Description:
Compressor station and pipeline maintenance
Month:
April 2026 and June 2026
Direction of Flow:
Delivery:
Spraberry 12-inch (Group 601) and Spraberry 16-inch (Group 1112)
Receipt:
Spraberry Station (Group 602)
Capacity Impact: Primary firm service
will be impacted for Spraberry 12-inch (Group 601), Spraberry 16-inch (Group
1112) and Spraberry Station (Group 602).
Revision: Capacity impacts for Spraberry
12-inch (Group 601), Spraberry 16-inch (Group 1112) and Spraberry Station
(Group 602) have been updated for May 2026 and included for June 2026.
Allocation Group(s)/Point(s):
Oasis Bakersfield Pecos Co. (POI 79340)
Location:
Northern’s compressor station located in Oasis, Texas
Project Description:
Compressor station maintenance
Month:
June 2026
Direction of Flow:
Delivery:
Oasis Bakersfield Pecos Co. (POI 79340)
Capacity Impact: Primary firm service
will be impacted for Oasis Bakersfield Pecos Co. (POI 79340).
Please see
Operationally Available Capacity
on
Northern’s website for current flow information and the
Field Area Group Allocation Maps
and
Market Area Group Allocation Maps
for a list of impacted points.
If you have any questions, contact your customer service or
marketing representative.