TSP Name:   Northern Natural Gas Company
TSP:   784158214
Notice ID:   091300
Notice Type:   Planned Service Outage
Subject:   PLANNED SERVICE OUTAGES – JUNE 2025 THROUGH OCTOBER 2025
Critical:   N
Location:   MARKET AND FIELD AREA
Post Date/Time:   06/06/2025 07:40 AM
Notice Effective Date/Time:   06/06/2025 07:40 AM
Notice End Date/Time:   11/01/2025 08:59 AM
For Gas Day(s):   06/05/2025 - 10/31/2025
Notice Status:   Supersede
Prior Notice:   091222
Required Response Indicator Description:   5-No response required
Notice Text:

Northern has scheduled the service outages that will affect operating capacity within the months of June 2025 through October 2025. Please review the Planned Service Outage Summary for detailed information related to each outage.

 

A brief description of the most recent change(s) to the Planned Service Outage Summary follows.

Northern received favorable results from an inspection of its mainline between Plainview, Texas, and Claude, Texas. As a result, capacity impacts for Beaver North (Group 1025), Beaver C and Beaver North (Group 1080), Brownfield North (Group 1022), Pampa North (Group 1023) and Beaver C System (Group 31) have been updated for the Intraday 1 nomination cycle for Gas Day Friday, June 6, 2025.

 

Field Area

Allocation Group(s)/Point(s): Beaver North (Group 1025), Beaver C and Beaver North (Group 1080), Brownfield North (Group 1022), Pampa North (Group 1023), Mitchell to Gaines (Group 825) and Beaver C System (Group 31)

Location: Northern’s compressor stations and mainline between Florey, Texas, and Mullinville, Kansas

Project Description: Station and pipeline maintenance

Month: June 2025 through August 2025

Direction of Flow:

       Receipt: Beaver C System (Group 31) and Mitchell to Gaines (Group 825)

Delivery: Beaver North (Group 1025), Beaver C and Beaver North (Group 1080), Brownfield North (Group 1022) and Pampa North (Group 1023)

Capacity Impact: Northern anticipates primary firm service will be impacted for Beaver C and Beaver North (Group 1080), Brownfield North (Group 1022) Pampa North (Group 1023) and Mitchell to Gaines (Group 825). Primary firm service will not be impacted for Beaver North (Group 1025) and Beaver C System (Group 31).

Revision: Capacity impacts for Beaver North (Group 1025), Beaver C and Beaver North (Group 1080), Brownfield North (Group 1022), Pampa North (Group 1023) and Beaver C System (Group 31) have been updated for June 2025.

 

Please see Operationally Available Capacity on Northern’s website for current flow information and the Field Area Group Allocation Maps and  Market Area Group Allocation Maps for a list of impacted points.

 