Northern has scheduled the
service outages that will affect operating capacity within the months of April 2025
through October 2025. Please review the
Planned Service Outage Summary for detailed information related to each
outage.
A brief description of the
most recent change(s) to the Planned Service Outage Summary follows.
Northern completed
compressor station maintenance impacting Spraberry Station (Group 602) ahead of
schedule. As a result, capacity impacts for
the above-mentioned group have been updated for the
Intraday 1 nomination cycle for Gas Day Saturday, April 26, 2025.
Field Area
Allocation Group(s)/Point(s):
Spraberry Station (Group 602), Spraberry 12-inch (Group
601) and Spraberry 16-inch (Group 1112)
Location:
Northern’s mainline between Spraberry, Texas, and Gaines
County, Texas
Project Description:
Pipeline maintenance
Month:
April 2025 through May 2025
Direction of Flow:
Receipt:
Spraberry Station (Group 602)
Delivery: Spraberry 12-inch (Group 601) and Spraberry 16-inch (Group
1112)
Capacity Impact:
Northern does not anticipate primary firm service will be
impacted for Spraberry 12-inch (Group 601). Primary firm service will not be
impacted for Spraberry 16-inch (Group 1112) and Spraberry Station (Group 602).
Revision:
Capacity impacts for Spraberry Station (Group 602)
have been updated for April 2025.
Please see
Operationally
Available Capacity on Northern’s website for current flow information and the
Field
Area Group Allocation Maps and
Market
Area Group Allocation Maps for a list of impacted points.
If you have any questions, contact your customer service or
marketing representative.