Northern has scheduled the following service outages that will affect operating capacity within the months of November 2026 through December 2026.  Please review the Planned Service Outage Summary for detailed information related to each outage.

 

A brief description of the most recent change(s) to the Planned Service Outage Summary follows.

 

Northern completed compressor station maintenance in Brownfield, Texas ahead of schedule. As a result, capacity impacts for Beaver C & Beaver System North (Group 1080), Brownfield North (Group 1022), Pampa North (Group 1023) and Beaver C System (Group 31) have been updated for the Intraday 3 nomination cycle for Gas Day Thursday, November 5, 2026.

 

Field Area

Allocation Group(s)/Point(s): Beaver C & Beaver System North (Group 1080), Brownfield North (Group 1022), Pampa North (Group 1023) and Beaver C System (Group 31)

Location: Northern’s compressor stations and pipeline between Florey, Texas, and Mullinville, Kansas

Project Description: Compressor station maintenance

Month: November 2026

Direction of Flow:

Delivery: Beaver C & Beaver System North (Group 1080), Brownfield North (Group 1022) and Pampa North (Group 1023)

Receipt: Beaver C System (Group 31)

Capacity Impact: Primary firm service will be impacted for Brownfield North (Group 1022). Primary firm service will not be impacted for Beaver C System (Group 31). Northern does not anticipate primary firm service will be impacted for Beaver C and Beaver System North (Group 1080) and Pampa North (Group 1023).

Revision: Capacity impacts for Beaver C & Beaver North (Group 1080), Brownfield North (Group 1022), Pampa North (Group 1023) and Beaver C System (Group 31) have been returned to normal.

 

Please see Operationally Available Capacity on Northern’s website for current flow information and the Field Area Group Allocation Maps and Market Area Group Allocation Maps for a list of impacted points.

 

If you have any questions, contact your customer service or marketing representative.