Notice Text:
Northern has scheduled the
service outages that will affect operating capacity within the months of June 2024
through October 2024. Please review the
Planned Service Outage Summary
for detailed information related to each
outage.
A brief description of the
most recent change(s) to the Planned Service Outage Summary follows.
Northern has completed maintenance at its
Spraberry, Texas, compressor station ahead of schedule. As a result, Spraberry
12-inch (Group 601) and Spraberry 16-inch (Group 1112) will return to normal
operating capacity beginning with the Intraday 3 nomination cycle for Gas Day
Friday, June 7, 2024. Due to ongoing pipeline maintenance between Plymouth,
Texas, and Spraberry, Texas, operational capacity for Spraberry Station (Group
602) has been updated beginning with the Intraday 3 nomination cycle for Gas
Day Friday, June 7, 2024.
Field Area
Allocation Group(s)/Point(s):
Spraberry 12-Inch (Group 601), Spraberry 16-Inch (Group
1112) and Spraberry Station (Group 602)
Location:
Northern’s compressor station at Spraberry, Texas and
mainline between Plymouth, Texas and Spraberry, Texas
Project Description:
Station and Pipeline Maintenance
Month:
June 2024 and July 2024
Direction of Flow:
Delivery: Spraberry 12-Inch (Group 601)
and Spraberry 16-Inch (Group 1112)
Receipt: Spraberry Station (Group 602)
Capacity Impact:
Northern does not anticipate primary firm service will be
impacted for Spraberry 12-Inch (Group 601) and Spraberry Station (Group 602). Primary
firm service will not be impacted for Spraberry 16-Inch (Group 1112)
Revision: Capacity impacts for Spraberry
12-Inch (Group 601), Spraberry 16-Inch (Group 1112) and Spraberry Station
(Group 602) have been updated for June 2024.
Please see Operationally Available Capacity on
Northern’s website for current flow information and the Field Area Group Allocation Maps and Market Area Group Allocation Maps
for a list of impacted points.
If you have any questions, contact your customer service or
marketing representative.
|