Northern has scheduled the
service outages that will affect operating capacity within the month of November
2023. Please review the Planned Service Outage Summary for detailed information related to each
outage.
A brief description of the
most recent change(s) to the Planned Service Outage Summary follows.
Northern completed
scheduled maintenance impacting Beaver North (Group 1025), Beaver C &
Beaver North (Group 1080), Beaver C System (Group 31), Brownfield North (Group
1022), and Pampa North (Group 1023) ahead of schedule. As a result, the
above-mentioned allocation groups will return to normal operating capacity
beginning with Intraday 1 nomination cycle for Gas Day November 17, 2023.
Field Area
Allocation Group(s)/Point(s): Beaver North (Group 1025), Beaver C & Beaver North (Group 1080), Beaver C System (Group
31), Brownfield North (Group 1022), and Pampa North (Group 1023)
Location: Compressor stations located in Brownfield, Texas, Pampa,
Texas, and Mullinville, Kansas
Project Description: Station maintenance
Months: November 2023
Direction of Flow:
Receipt:
Beaver C System (Group 31)
Delivery: Beaver North (Group 1025),
Beaver C and Beaver North (Group 1080), Brownfield North (Group 1022) and Pampa
North (Group 1023)
Capacity Impact: Primary firm service will not be impacted for Beaver C & Beaver North (Group 1080), Beaver C System (Group 31) and Beaver North (Group 1025).
Northern does not anticipate primary firm service to be impacted for Brownfield North (Group 1022), and Pampa North
(Group 1023)
Revision: Capacity impacts for Beaver North (Group 1025), Beaver C & Beaver North (Group 1080), Beaver
C System (Group 31), Brownfield North (Group 1022), and Pampa North (Group
1023) have been removed for November 2023.
Please see Operationally
Available Capacity on Northern’s website for current flow information and the Field
Area Group Allocation Maps and Market
Area Group Allocation Maps for a
list of impacted points.