Resources

 
Map of Project Scope

 

 Regulatory Filings and Issuances

 
Notice of Start of Construction on the Carver Compressor Station

FERC Approval to Commence Construction on the Carver Compressor Station

SHPO and THPO Concurrence and Request to Commence Construction on Carver Compressor Station

Supplemental Cultural Report for Rochester Greenfield Lateral – Condition 15 –Public Information

Northern’s Notice of Start of Construction on the Owatonna and Faribault Compressor Stations

Northern’s Biweekly Report

Supplemental Cultural Report for Alexandria Branch Loop Extension in Accordance with Condition 15

Northern’s Supplemental Response to Condition 15 (Public Information)

Northern’s Supplemental Response to Condition 15 of the FERC Order

FERC Approval of the New Prague Variances

FERC Approval to Commence Construction on the Owatonna and Faribault Compressor Stations and the New Prague Branch Line

Northern’s Supplemental Correspondence With the U.S. Fish and Wildlife Service

Northern Natural Gas’ Supplemental Information

Northern’s Responses to Conditions of FERC Order (Condition 1 – Condition 5/Alignment Sheets)

Northern’s Responses to Conditions of FERC Order (Condition 5/Alignment Sheets)

Northern’s Responses to Conditions of FERC Order (Condition 5/Alignment Sheets)

Northern’s Responses to Conditions of FERC Order (Condition 5/HDD Plan and Profiles/Site-Specific Plans)

Northern’s Responses to Conditions of FERC Order (Condition 5/HDD Plan and Profiles/Site-Specific Plans)

Northern’s Responses to Conditions of FERC Order (Condition 5/HDD Plan and Profiles/Site-Specific Plans)

Northern’s Responses to Conditions of FERC Order (Condition 5/HDD Plan and Profiles/Site-Specific Plans)

Northern’s Responses to Conditions of FERC Order (Condition 5/ROW Typicals/HDD Feasibility Studies/HDD Contingency Plans – Condition 18)

FERC Order

FERC’s Environmental Assessment

FERC’s Notice of Application

Section 7 Application and Resource Report 1

FERC’s Notes for February 20, 2018, Biweekly Conference Call

FERC’s Notes for February 6, 2018, Conference Call

Northern’s February 2018 Monthly Report

FERC’s Errata Notice for the Notice of Intent to Prepare an Environmental Assessment

FERC’s Notice of Intent to Prepare an Environmental Assessment

FERC’s Notes for January 23, 2018, Conference Call

Northern’s January 2018 Monthly Status Report

FERC’s Notes for December 28, 2017, Conference Call

Northern’s Revised Draft Resource Report 10

Northern’s Responses to Stakeholder Comments

Northern’s December 2017 Monthly Status Report

Northern’s November 2017 Monthly Status Report

Draft Resource Reports 1 and 10 – Mapbook

Draft Resource Reports 1 and 10

Northern’s Responses to Landowner Comments Received at the October 2017 Open Houses

FERC Approval to Use the Pre-Filing Process

Northern’s Request to Use the Pre-Filing Process

Northern Lights 2019 - Rochester Expansion

 
Project Overview

On July 27, 2018, Northern filed a section 7 application with the Federal Energy Regulatory Commission for the Northern Lights 2019 Project. The project is composed of two discrete projects, the Northern Lights 2019 Expansion component and the Rochester Expansion component; the two projects will be built at the same time and both projects are contained in the application with the Federal Energy Regulatory Commission. The project is docketed at CP18-534-000.
 
The proposed facilities include, for the Rochester project: (1) construction of 12.24 miles of 16-inch-diameter greenfield branch line; (2) an increase in the maximum allowable operating pressure (MAOP) of an 8.04-mile segment of the La Crosse branch line; and (3) a new Rochester town border station (TBS).
 
The Northern Lights 2019 segment of the project will consist of construction of: (1) 10-miles of 24-inch-diameter greenfield pipeline in Hennepin and Wright counties, Minnesota; (2) approximately 9 miles of branch line and mainline loops/extensions, ranging in size from 6-inch- to 36-inch-diameter pipeline, I Morrison, Le Sueur, and Carver counties, Minnesota; (3) additional compression at Northern’s existing Faribault and Owatonna compressor stations in Rice and Steele County, Minnesota, respectively; and (4) a new compressor station located near Carver, Minnesota.
 
The project is required to meet the growing energy requirements of Northern’s customers serving the state of Minnesota. All facilities, as described in the table, will be located within Minnesota.
 
The proposed routes, including the greenfield branch lines and the new compressor station site, were selected after analysis of engineering options, route/site options, and Project alternatives with an effort to minimize impacts to the environment and the number of affected landowners. The proposed pipeline loops and extensions will utilize existing pipeline corridors. The proposed site for the Carver, Minnesota, compressor station was selected due to its strategic location on Northern’s existing system.
 
On November 21, 2018, Commission staff issued its Environmental Assessment for the project. Among other standard conditions, staff also is recommending (1) the proposed 50 foot offset between the proposed and adjacent pipelines be rejected and that Northern Natural Gas install the branch lines with a maximum 25-foot offset from the adjacent pipeline; (2) a noise survey should be filed for the Rochester town border station and for the maximum allowable operating pressure regulator; and (3) prior to conducting night time horizontal directional drill activities, a noise mitigation plan must be filed and approved by the Commission. Comments to the environmental assessment were due December 21, 2018.

Content on this site requires Adobe Acrobat Reader. Click on the Adobe icon to download a free version of the program to your computer.
 

 Safety & Environment

 
Environment

Safety