                                      GENERAL TERMS AND CONDITIONS

                        Measuring Equipment Out of Repair.  If, for any reason, any
                        measuring equipment is out of service or out of repair so that
                        the quantity of gas delivered is not correctly indicated by the
                        reading thereof, the gas delivered during such period shall be
                        estimated by the parties on the basis of the best data available
                        using the first of the following methods which is feasible:

                        a)  By using the registration of any check measuring equipment
                            installed and accurately registering; or

                        b)  By correcting the error if the percentage of error is
                            ascertainable by calibration, test or mathematical
                            calculations; or

                        c)  By estimating the quantity of delivery by deliveries during a
                            preceding period under similar conditions when the meter was
                            registering accurately.

                        Adjustment of Inaccuracies.  If any meter is found to be
                        inoperative or inaccurate, it shall be adjusted to register
                        correctly.  The amount of error shall be determined by the most
                        accurate method found feasible, and, if the error shall have
                        resulted in an error of more than two percent (2%) in the
                        measurement of gas delivered, then the calculated deliveries of
                        gas through such meter shall be accurately adjusted to compensate
                        for such error.  Such adjustment shall be made for such period of
                        inaccuracy as may be definitely known, or if not known, then for
                        one-half the period since the date of the last meter test.
                        Measurement data corrections must be processed within six (6)
                        months of the production month with a three (3) month rebuttal
                        period.  This time limitation will not apply in the case of
                        deliberate omission or misrepresentation or mutual mistake of
                        fact.  Also, the parties' other statutory or contractual rights
                        shall not otherwise be diminished by this provision.  A meter
                        adjustment or correction becomes a prior period adjustment after
                        the fifth business day following the production month.  Any
                        measurement prior period adjustments are taken back to the
                        production month.

               3.  MERCHANTABLE GAS
                   ----------------

                   Natural gas delivered by Northern to a Shipper shall be merchantable
                   natural gas.  Upon request, Northern will offer to negotiate with a
                   Delivery Point Operator, on a not unduly discriminatory basis, how
                   Northern will manage the quality of gas delivered to the Delivery
                   Point Operator.  The quality of gas delivered to other Shippers
                   on the pipeline will not be degraded by the negotiation of gas quality
                   management at delivery points.






Issued by: Mary Kay Miller, V.P. Regulatory & Government Affairs
Issued on: July 15, 2005                                                     Effective: July 5, 2005
Filed to comply with order of the Federal Energy Regulatory Commission,
Docket No. RP05-370-000, issued July 1, 2005, 112 FERC 61,008